Cold-Planing (Milling) Production and RAP Tonnage

Square yards per hour a cold planer cuts and the reclaimed-asphalt (RAP) tonnage it makes, which sizes the haul fleet.

Run the calculator

Example

You enter

You get

Details, formula, and sources

sy/hr = drum width x speed x 60 x efficiency / 9; RAP tph = sy/hr x depth x density x 0.75 / 2000. A 7 ft drum at 30 ft/min covers 980 sy/hr, and a 4 in cut of 148 pcf pavement is ~218 tph of RAP - a truck every three minutes, or the mill stops. Field conditions govern the efficiency.

sy_per_hr = drum_width_ft x speed_fpm x 60 x efficiency / 9; spread_lb_per_sy = depth_in x density_pcf x 0.75; rap_tph = sy_per_hr x spread_lb_per_sy / 2000.

Cold-planing production identity by name (area rate from drum/speed/efficiency; RAP from area rate x spread); first-principles production arithmetic.

The production and RAP geometry are public first-principles arithmetic; the efficiency comes from field conditions.

Estimate. AHJ and licensed professional govern.

Field names used by the API: drum_width_ft, speed_fpm, depth_in, density_pcf, efficiency, sy_per_hr, spread_lb_per_sy, rap_tph