Stabilized Construction Entrance Stone

Cubic yards and tons of coarse stone for a stabilized construction entrance (track-out BMP).

Run the calculator

Example

You enter

You get

Details, formula, and sources

tons = length x width x depth x unit weight / 2000. The common 50 ft x 14 ft x 6 in pad is 13 cy (~17.5 tons) - the load on site before the first truck rolls out. The geotextile separator under the pad is taken off separately; the AHJ sets the size.

volume_cy = length_ft x width_ft x (depth_in/12) / 27; tons = length_ft x width_ft x (depth_in/12) x unit_wt_pcf / 2000.

Pad take-off identity by name (length x width x depth x unit weight); first-principles volume arithmetic.

The pad take-off is public quantity-survey geometry; the pad dimensions come from the general permit or AHJ.

Estimate. AHJ and licensed professional govern.

Field names used by the API: length_ft, width_ft, depth_in, unit_wt_pcf, volume_cy, tons