EGC for Parallel Raceways (NEC 250.122(F))

The equipment grounding conductor for each raceway of a paralleled feeder, per NEC 250.122(F).

Run the calculator

Example

You enter

You get

Details, formula, and sources

Each raceway of a paralleled feeder needs its OWN full-size EGC sized to the WHOLE circuit's device - the EGC is not divided among sets the way the ungrounded conductors are. A 400 A feeder in 2 raceways takes two #3 copper, not the #6 that sizing from 200 A would give. A ground fault returns through THAT raceway's EGC alone. Flags the 2026 NEC revision, which changes the answer.

Each parallel raceway carries a full-size EGC sized from Table 250.122 to the WHOLE circuit's overcurrent device rating; total EGC runs = number of raceways. The EGC is not divided among the parallel sets.

NEC 250.122(F), equipment grounding conductors for conductors in parallel, by section number - the 2023-and-earlier rule; no table is reproduced here because the sizing is delegated to this catalog's existing egc-sizing model.

The NEC is viewable free through the NFPA online access portal; 250.122 is in every adopted edition.

Estimate. AHJ and licensed electrician govern. Verify against the NEC edition adopted in your jurisdiction.

Field names used by the API: ocpd_A, raceway_count, material, egc_per_raceway_awg, total_egc_count, divided_ocpd_A, undersized_awg